2026 Global Data Center Outlook
AI and cloud to drive 14% CAGR in data centers through to 2030
The data center sector is projected to increase by 97 GW between 2025 and 2030, effectively doubling in size over a five-year period. By 2030, global data center capacity could reach 200 GW. This rapid growth will be driven largely by hyperscale cloud expansion and AI demand.
The Americas is the largest data center region, representing about 50% of global capacity. The Americas also has the fastest growth rate of the three global regions, with a projected 17% supply CAGR through to 2030, preserving its position as the dominant data center region. The U.S. drives most of the activity in the region, accounting for about 90% of capacity in the Americas.
APAC data center capacity will expand from 32 GW to 57 GW by 2030, achieving a 12% CAGR. Colocation leads growth at 19%, while on-prem capacity is projected to decline 6% as enterprises continue cloud migration.
EMEA’s 10% CAGR forecast is fueled by government support for AI infrastructure and strong demand for sovereign AI clouds to meet data privacy regulations. The region will add 13 GW of new supply, with growth concentrated in established European hubs and emerging Middle Eastern markets pursuing digital transformation strategies.
AI could represent half of data center workloads by 2030
While AI has been quickly gaining daily active users, it only represented about a quarter of all data center workloads in 2025, with training driving most of the demand. However, a significant shift is anticipated in 2027, when inference workloads could overtake training as the dominant AI requirement.
While an AI model represents a one-time or periodic investment, once the model is created, inference generates ongoing revenue through actual application usage. Looking forward, every AI model deployment creates sustained inference demand that grows with user adoption. This growth, however, depends on the emergence and rapid adoption of inference applications that don't yet exist at scale.
Inference demand requires geographical distribution to reduce latency and serve users effectively. This will drive regional deployments and embedded systems at the edge.
Data center construction costs have been increasing at 7% CAGR
The industry is expanding at a relentless pace, resulting in extended lead times, limited availability of skilled trades and escalating development costs.
Between 2020 and 2025, the average global data center construction cost increased from $7.7 to $10.7 million per MW, equating to 7% CAGR. For 2026, JLL is forecasting the average global cost will increase 6% to $11.3 million per MW.
Speed to power is the primary criteria driving site selection, followed by community support, latency and proximity to customers. However, as project sizes get larger, variations in construction costs may weigh more heavily in location decisions.
Note: the figures in the chart only include the cost to construct the shell and core. Tenants are typically responsible for the tech fit-out which can cost as much as $25 million per MW for AI infrastructure.
$3 trillion investment required for 100 GW of new supply by 2030
The global data center sector is estimated to grow at a 14% CAGR over the next five years, which could result in 100 GW of new capacity coming online including hyperscale, colocation and on-prem facilities. This equates to $1.2 trillion in real estate asset value creation and a need for roughly $870 billion of new debt financing.
The figures above do not include the $1 to $2 trillion that tenants will spend to fit out their space with GPUs and networking infrastructure, meaning that total data center expenditures over the next five years could approach $3 trillion. Taken all together, it is safe to say that we are in the midst of an infrastructure investment supercycle.
New data center projects are getting larger and more expensive to build. As a result, the sector continues to consolidate due to the immense development costs coupled with the increasing sophistication required to build and operate modern data centers.
These expanding barriers to entry are removing some of the speculation from the development queue and accelerating viable projects backed by credible companies. For these groups, debt markets will remain open for business.